The Outcome Dependencies Tab

Use the Outcome Dependencies tab to view and enable/disable outcome dependencies.

Click image to expand or minimize. 

This interface shows us the resultant weight of the dependent Opportunity Outcome for each Outcome of the independent Opportunity. So, for example, in the screenshot above, if the Outcome “Fail” is chosen for the independent project (GoM Exploration Well #1) during a Monte Carlo simulation, the dependent projects weights will be 75% for fail, 5% for P50, 20% for P90, and 0% for P10.